Tentative Work Schedule

August 13, 2019

 

Work in the NW section consists of Mowing an Outfall Ditch on NW CR 235

 

Work in the SE section consists of Grading SE 26th Ave., SE 50th, SE 31st (Off Immokalee Road), Install culverts at SE 144th St. & SE 129th St., Fill in drop off at 671 SE 73rd St. with milling  and Mow off of Immokalee Road

 

Work in the SW section consists of Grading SW 132nd Ave., SW 168th St. & SW 130th Pl.

 

 

We received 3 DOC Squads for a total of 17 people

 

1 Squad will be Weed eating NW 71st Ave., NW 74th Ave. & NW 41st Ave.

 

1 Squad will be Weed eating SW CR 225 (3 Pipes) and Picking up trash on Market Road & NW CR 233

 

1 Squad will be directing traffic for installing culverts on SE 144th St. & SE 129th St