Tentative Work Schedule

November 28, 2018

 

Work in the NW section consists of Zipping NW 185th St.

 

Work in the SE section consists of Moving equipment and Pull Ditches on SE 125th Ter., Mowing SE 144th, SE 142nd and SE 150th with the Side Arm and Mowing SE CR 21B

 

Work in the SW section consists of Grading SW 163rd, SW 85th and SW 105th, Taking down and putting back up Guardrail on SW 106th

 

 

We received 3 DOC Squads for a total of 16 people

 

1 Squad will be Taking down Guardrail and put it back up on SW 106th

 

1 Squad will be Picking up trash and Weed eating NW CR 235 and then back to SW CR 227

 

1 Squad will be helping take up guardrail and putting it back down on SW 106th