Tentative Work Schedule

June 8, 2022

 

Work in the NE section consists of Cleaning out Ditches on NE 18th Ave. and Mowing around Mailboxes, Culverts, Guardrails and Signs on NE CR 225, NE 17th Ave. and in the Starke Golf and Country Club area

 

Work in the NW section consists of  Trimming Trees on NW CR 225 between NW 180th St. and NW 185th St. and Mowing ROW on NW 44th Ave.

 

Work in the SE section consists of Grading SE 43rd, SE 41st, SE 101st, SE 101st, SE 11th and in Crystal Lake Homesites area, Dig Ditches on SE 49th Ave. and Mowing SE CR 21B, SE 8th Ave. and SE CR 214

 

Work in the SW section consists of Picking up limbs and debris on SW 82nd Ave.

 

 

We received 2 DOC (BCSO-JAIL) Officers and a total of 4 Inmates.  They will be Trimming, Weed Eating and Cleaning up at the SE 51st St. Retention Pond site