Tentative Work Schedule

March 28, 2019

 

Work in the NE section consists of Finish Digging the ditch on NE 154th Ter. and Patching driveways and pot holes on NE 17th Ave. in Lawtey

 

Work in the NW section consists of Grading and Packing NW 219th St., Digging the ditch on NW 53rd Ave., Installing a culvert on NW 71st Ave. and Patching Driveways and Pot holes on NW 177th (Pleasant Grove area)

 

Work in the SE section consists of Grading SE 31st Ave. and SE 51st

 

Work in the SW section consists of Grading and Packing SW 106th Ave. and Patching shoulders on SW CR 18

 

We received 3 DOC Squads for a total of 11 people

 

1 Squad will be Picking up trash and weed eating on SE 21st Ave. (bags dropped off) and NW CR 125

 

1 Squad will be patching driveways and pot holes on NW 177th then NE 17th Ave

 

1 Squad will be directing traffic for digging the ditch on NE 154th Ter. and Install a culvert on NW 71st Ave.