Tentative Work Schedule

April 3, 2019

 

Work in the NE section consists of Putting concrete down on NE 160th St. and Patching driveways on NE 20th Ln.

 

Work in the NW section consists of Grading NW 219th St., NW 71st, NW 75th & NW 185th., Patching driveways on NW 177th St. and Digging the ditch on NW 53rd Ave

 

Work in the SE section consists of Sealing SE 49th Ave. behind Hampton Elementary School

 

 

We received 3 DOC Squads for a total of 14 people

 

1 Squad will be Patching Driveways on NE20th Lane and NW 177th St.

 

1 Squad will be Picking up trash and Weed Eating on SE 109th

 

1 Squad will be Picking up Trash and Weed Eating on SE CR 100A