Tentative Work Schedule

September 26, 2019

 

Work in the NE section consists of Grading NE 173rd St. and NE 204th St.

 

Work in the NW section consists of Grading NW 219th (53rd end), NW 257th St and NW 219th St (off NW CR 225 end), Cleaning out a ditch on NW CR 235 and Mowing NW 41st Ave.

 

Work in the SE section consists of Mowing SE CR 21B, SE 8th Ave. and SE 35th St.

 

Work in the SW section Patching Pot Holes on SW CR 18 and Mowing SW CR 231 (Dedan Loop)

 

 

We received 3 DOC Squads for a total of 12 people

 

2 Squads will be Picking up trash and weed eating on NW 71st, starting on NW CR 229A end and going South

 

1 Squad will be directing traffic and assisting in patching pot holes on SW CR 18