Tentative Work Schedule

September 28, 2023

 

Work in the NW section consists of Grading NW 238th St., NW 25th Ave. and NW 257th St., Mow Shoulders of the Road on NW 251st St., NW 247th St. and NW 238th St. and Pick Up Tree and Debris on NW 267th St.

 

Work in the SE section consists of Grading SE 71st St., SE 72nd St. and SE 73rd St.

 

Work in the SW section consists of Grading SW 66th Ave. and Mowing SW CR 231, SW 175th Ave. and SW CR 237

 

 

We received 2 DOC (BCSO-JAIL) Officers and 3 Inmates and they will be Weed Eating the Intersection at SW CR 18 and SW CR 227 and the Guardrail on NW CR 225 near NW 212th St.