Tentative Work Schedule

April 25, 2019

 

Work in the NE section consists of Grading NE 247th and Patching pot holes on NE 179th St.

 

Work in the NW section consists of Grading NW 267th & NW 257th and Mowing NW CR 125

 

Work in the SE section consists of Cleaning out the ditch on SE 23rd Ave. and Cutting and Hauling off trees

 

Work in the SW section consists of Adding milling & Grading SW 106th Ave., Grading SW 168th St., Chipping debris on SW 132nd Ave. and Patching troughs at the intersection of SW CR 18 & US Hwy. 301

 

 

We received 3 DOC Squads for a total of 11 people

 

1 Squad will be Chipping debris on SW 132nd Ave.

 

1 Squad will be Picking up Trash and Weed Eating NW 27th Ave. and NW CR 225A

 

1 Squad will be Cutting and Hauling trees on SE 23rd Ave. and Patching Pot Holes on NE 179th St.