Tentative Work Schedule

April 11, 2019

 

Work in the NE section consists of Digging the ditch on NE 19th Ave.

 

Work in the NW section consists of Zipping and Grading NW 219th St, Grade NW 212th St., NW 74th & NW 215th, Clean up and Haul away roots and sticks on NW 53rd Ave. ditch and Fill in shoulders on NW CR 225 between SR 100 and NW CR 229

 

 

We received 3 DOC Squads for a total of 14 people

 

1 Squad will be Cleaning up and Hauling off Roots, Stumps and Sticks on NW 53rd Ave. ditch

 

1 Squad will be Filling in Shoulders on NW CR 225 between SR 100 and NW CR 229

 

1 Squad will be directing traffic and Digging the Ditch on NE 19th Ave.