Tentative Work Schedule

January 7, 2019

 

Work in the NE section consists of Grading off 301 coming South from Lawtey and Patching pot holes on Carter Road (Lawtey)

 

Work in the NW section consists of Grading off 301 coming South from Lawtey, Patching pot holes on NW CR 235 and NW 132nd Pl. and Installing culverts on NW 188th & NW 84th for Eric Reddish

 

Work in the SE section consists of Grading SE 49th, SE 41st, SE 43rd, SE 44th, SE 48th and SE 87th

 

Work in the SW section consists of SW 92nd, SW 105th and SW 163rd

 

 

We received 3 DOC Squads for a total of 16 people

 

1 Squad will be Patching pot holes on NW CR 235 & NW 132nd Pl.

 

1 Squad will be Patching pot holes on Carter Road in Lawtey

 

1 Squad will be Picking up trash and weed eating on NW CR 125