Tentative Work Schedule

March 14, 2022

 

Work in the NE section consists of Cleaning out Culverts on NE 219th St.

 

Work in the NW section consists of Grading NW 44th Ave., Patching a Driveway on 19660 NW CR 235 and Mowing NW 37th Lane

 

Work in the SE section consists of Adding Limerock and Grading SE 101st Ave.

 

Work in the SW section consists of Adding Limerock and Grading SW 66th Ave.

 

 

1 DOC (BCSO-JAIL) Officer will be Picking up Compressors for Dale Hayes