Tentative Work Schedule

March 23, 2021

 

Work in the NE section consists of Mowing ROW on NE 223rd and Watering NE 204th St.

 

Work in the NW section consists of Grading NW 212th St. and NW 203rd St. and Watering NW 185th St.

 

Work in the SE section consists of Grading SE 50th and SE 20th Ave. and Mowing SE CR 100A and SE CR 230A

 

Work in the SW section consists of Installing a Crossover pipe on SW 132nd Ave. and Mowing SW CR 225 and the Sidewalk and Boat Ramp around Hampton Lake with the Zero Turn

 

 

We received 1 DOC Squads for a total of 6 people

 

1 Squad will be Picking up trash and weed eating on SE 144th St. (Vystar Road) and SE 21st Ave.