Tentative Work Schedule

June 3, 2019

 

Work int he NW section consists of Grading NW 84th Ave. & NW 219th St. (Off NW 44th Ave.), Shoulder work on NW 84th Ave. and Adding milling to a driveway on NW CR 235

 

Work in the SE section consists of Patching driveways on SE 150th St.

 

Work in the SW section consists of Picking up trees at the Sampson Lake Boat Ramp, Mowing SW CR 225, SW CR 18 starting at SW CR 18 & SW CR 227 and go toward 301 and Trimming limbs on SW 75th Ave. & SW 180th Pl.

 

 

We received 3 DOC Squads for a total of 16 people

 

1 Squad will be Picking up trash & weed eating SW CR 225

 

1 Squad will be Picking up trash & weed eating SW CR 18

 

1 Squad will be finishing Weed eating NW 105th Ave., Working on shoulders on NW 84th Ave. and Filling in driveway on NW CR 235