Tentative Work Schedule

 

July 18, 2018

 

Work in the NW section consists of Build up & Grade NW 41st Ave. and Pull Ditches on NW 71st Ave.

 

Work ion the SE section consists of Digging Ditches in Lincoln City

 

Work in the SW section consists of Adding Clay and Enzymes to SW 101st Ave., Patching troughs on SW CR 235, Mowing SW CR 235 and SW CR 231

 

 

We received 2 DOC Squads for a total of 11 people

 

1 Squad will be Patching troughs on SW CR 235

 

1 Squad will be directing traffic for Digging Ditches in Lincoln City