Tentative Work Schedule

March 9, 2023

 

Work in the NW section consists of Grading NW 214th, NW 110th, NW 198th, NW 194th, NW 122nd, NW 251st, NW 28th and NW 228th

 

Work in the SE section consists of Cleaning out a Ditch on SE 9th Ave. and Oversee SE 49th Ave. project

 

Work in the SW section consists of Patching Shoulders on SW 75th and SW CR 225

 

We will be Picking up Tree Debris all over the County

 

 

We received 1 DOC Officer and 3 Inmates and they will be Picking up Trash on SW CR 225