Tentative Work Schedule

May 6, 2021

Work in the NE section consists of Mowing NE 17th Ave. and NE 14th Ave.

 

Work in the NW section consists of Grading NW 41St. Ave., NW 44th, NW 70th and NW 219th Ter., Patching Pot Holes on NW 200th St. and Mowing ROW on NW 53rd Ave. and NW 219th St.

 

Work in the SE section consists of Grading SE 125th St., SE 59th St., SE 94th St. and SE 45th, Mowing SE CR 230A and SE 150th St. and Installing a culvert next to the Santa Fe Boat Ramp on SE CR 21B

 

Work in the SW section consists of Grading SW 87th, Shoulder work on SW CR 18 and Lowering a culvert on SW 65th Ave.

 

 

We did not receive any DOC Squads nor any Inmates