Work Schedule

 

Work in the NE section consists of Grading

 

Work in the NW section consists of Grading, Mowing, Digging ditches, Pulling ditches and Patching/Repairing Bridge

 

Work in the SE section consists of Zipping & Milling two roads

 

Work in the SW section consists of Grading

 

 

We received 3 DOC Squads for a total of 18 people.

 

1 Squad will be weed eating and Picking up trash in the SW section

 

1 Squad will be Picking up trash in the SE section

 

1 Squad will be assisting with Traffic Control, weed eating and Picking up trash in the NW section

 

 

1 Squad from The Transition House (3 people) will be assisting in patching driveways and Bridge