Tentative Work Schedule

March  27, 2019

Work in the NE section consists of Installing a culvert on NE 154th Ter

Work in the NW section consists of Grading and Packing NW 219th St. (Off NW CR 225) and dig the ditch on NW 53rd

Work in the SE section consists of Grading SE 71st, SE 73rd, SE 4th, SE 5th and SE 7th

Work in the SW section consists of Grading SW 163rd, SW 66th, SW 162nd,SW 163rd & SW 155th St., Install a culvert on 1464 SW CR 100A, Patch pot holes in the City of Brooker and Fill in shoulders on SW CR 18

 

We received 3 DOC Squads for a total of 17 people

1 Squad will be Picking up Trash and Weed eating on NE 20th Lane

1 Squad will be Patching pot holes in the City of Brooker

1 Squad will be directing traffic for installing culverts