Work Schedule

 

 

Work in the NW section consists of Zipping and Hauling Clay to be used with the Zipper.

 

Work in the SE section consists of Patching driveways, Mowing and Cutting leaning trees and Chipping

 

Work in the SW section consists of filling in washouts and Grading on a Private Road

 

 

We received 3 Squads for a total of 18 people

 

1 Squad will assist in Cutting leaning trees & brush in the SE section

 

1 Squad to pick up trash and weed eat around mailboxes and driveways in the SE section

 

1 Squad directing traffic for installing culverts in the NE  and SE section

 

 

1 Squad from The Transition House (2 people) patching driveways