Tentative Work Schedule

September 11, 2019

 

Work in the NE section consists of Repair/Concrete sidewalk on NE 17th Ave.

 

Work in the SE section consists of Grading SE 31st St., SE 50th, SE 51st and SE 50th (off of 21B on the lake side)

 

Work in the SW section consists of Grading SW 163rd St., SW 132nd Ave., SW 168th & SW 144th, Cut shoulders down & limerock SW 155th Ave. and Mow SW CR 231 & SW CR 237

 

 

We received 2 DOC Squads for a total of 8 people

 

1 Squad will be Repairing and concreting the side walk on NE 17th Ave.

 

1 Squad will be assisting with Cutting the shoulders down and limerocking SW 155th Ave.