Tentative Work Schedule

November 2, 2020

Work in the NE section consists of Cutting ROW on NE 17th 

 

Work in the NW section consists of Prepping NW 124th and Cutting, Trimming, Chipping and Mulching limbs on NW CR 125

 

Work in the SE section consists of Grading SE 4th, SE 5th, SE 7th, SE 71st, SE 72nd & SE 73rd, Picking up trees on SE 2nd Ave. and Mowing SE 21st and SE 144th

 

Work in the SW section consists of Grading SW 155th, SW 132nd and SW 180th and Picking up trees on SW CR 231 and SW 161st

 

 

We received 1 DOC Squad and has a total of 5 people and will be Assisting with Picking up trees on SW CR 231, SW 161st and SE 2nd Ave. and then go to assist with Chipping on NW CR 125.