Tentative Work Schedule

March 27, 2024

 

Work in the NW section consists of Grading at Market Road Pit, Patching Pot Holes on NW 219th St. (off NW CR 225) and  Prepping NW 38th Ave.

 

Work in the SE section consists of Grading SE 72nd St., SE 73rd St. and SE 94th St.

 

Work in the SW section consists of Grading SW 155th St., SW 160th Ave. and SW 136th St.

 

We will be Loading and Hauling Dirt to the New River Solid Waste Landfill

 

 

We received 2 DOC (BCSO-JAIL) Officers and 2 Inmates

 

1 Officer will be assisting Maintenance Department

 

1 Officer and 2 Inmates will be Picking up Trash on NW 44th Ave. and NW 219th St.