Tentative Work Schedule

December 18, 2019

 

Work in the NW section consists of Grading NW 219th St. and Cleaning out a ditch on NW CR 235

 

Work in the SE section consists of Grading SE 49th Ave., SE 41st Ave. and SE 4th Ave.

 

Work in the SW section consists of Shoulder work on SW CR 235 and Mowing SW 101st Ave. and SW CR 225

 

 

We received 2 DOC Squads for a total of 10 people

 

1 Squad will be directing traffic for digging out a ditch on NW CR 235

 

1 Squad will be directing traffic for shoulder work on SW CR 235