Tentative Work Schedule

September 16, 2020

 

Work in the NE section consists of Grading NE 6th Lane and NE 154th Way (Private Roads-State of Emergency)

 

Work in the NW section consists of Mowing and Trimming ROW on NW 82nd St. & NW 44th

 

Work in the SE section consists of Grading SE 49th Ave., SE 41st Ave. and SE 43rd Ave.

 

Work in the SW section consists of Grading SW 83rd & SW 128th Way (Private Roads-State of Emergency)

 

 

We received 2 DOC Squads for a total of 10 people

 

1 Squad will be Chipping limbs On SW CR 231 (Dedan Loop)

 

1 Squad will be Weed eating ROW on NE 223rd St.