Tentative Work Schedule

March 4, 2020

 

Work in the NE consists of Patching a driveway on NE 17th Ave.

 

Work in the NW section consists of Zipping & Prepping NW 219th St.for Fog Sealing and grading NW 55th Lane & NW 62nd Ave.

 

Work in the SW consists of Grading SW 163rd St. & Finish Grading SW 104th Ave and Filling in troughs on SW CR 18

 

 

Inmates from LCI were on lockdown and did not get any DOC Inmates

 

Had 1 Squad with BCSO Inmates (2) and they were directing Traffic and assisting with Patching troughs on NE 17th Ave.