Tentative Work Schedule

January 30, 2020

 

Work in the NE section consists of Picking up Sod and laying it on NE 15th Pl

 

Work in the NW section consists of Grading off of NW CR 125 and go towards the River

 

Work in the SE section consists of Picking up dead tree and Hauling off on SE 21st Ave., Grade, Pack and Begin Fog Seal on SW 101st Ave. and Patch Pot Holes on Tetstone Ave. in Brooker

 

 

We received 3 DOC Squads for a total of 14 people

 

1 Squad will be Picking up trash and Weed eating on NW CR 225

 

1 Squad will be directing traffic on SW 101st Ave. for Fog Sealing

 

1 Squad will be laying Sod on NE 15th Pl