Tentative Work Schedule

April 19, 2022

 

Work in the NE section consists of Grading NE 26th Ave. and Mowing ROW on NE 18th Ave.

 

Work in the NW section consists of Grading NW 38th Ave. and NW 132nd Pl. and Repairing Crossover pipes on NW CR 235

 

Work in the SE section consists of Grading SE 46th Loop and Mowing SE 21st Ave. and SE 144th

 

 

We received 2 DOC (BCSO-JAIL) Officers and the Inmates were on Lock Down, so we did not get any.  The 2 DOC Officers will be assisting with the Repair of the Crossover pipes on NW CR 235