Tentative Work Schedule

October 9, 2019

 

Work in the NE section consists of Mowing ditches on NE 19th Ave. and Mow NE CR 225 and NE CR 125

 

Work in the NW section consists of Grading NW 219th St., Mowing NW 183rd, NW 184th, NW 216th and NW CR 225

 

Work in the SE section consists of Grading SE 49th, SE 86th and Dig Ditches on SE 21st Ave.

 

Work in the SW section consists of Grading SW 168th, SW 144th, SW 137th, SW 155th, SW 160th and SW 136th and Patch troughs on SW CR 235

 

 

We received 3 DOC Squads for a total of 14 people

 

1 Squad will be Picking up Trash and Weed Eating Lincoln City

 

1 Squad will be Cleaning out the Ditch on SW CR 235

 

1 Squad will be directing traffic for Digging Ditches on SE 21st Ave.