Tentative Work Schedule

November 24, 2020

 

Work in the NE section consists of Grading NE 20th Lane

 

Work in the NW section consists of Grading NW 45th Ave., NW 205th and NW 219th, Shoulder work on NW CR 225, Patch driveways on NW 57th Pl. and Filling in coming off of NW 22nd Ave. onto NW 247th St. and Mowing NW CR 229 and NW CR 233

 

Work in the SE section consists of Prepping and Spraying SE 1st St.

 

Work in the SW section consists of Mowing SW CR 100A and SW 75th Ave.

 

 

We received 3 DOC Squads for a total of 12 people

 

1 Squad will be picking up trash and weed eating on SW CR 18

 

1 Squad will be Cleaning up a Rental Tractor to take back on 11/25/2020 then Picking up trash and weed eating on SE 129th St. and NW CR 225

 

1 Squad will be assisting with Patching driveways on NW 57th Pl. and then filling in at the Intersection of NW 22nd Ave. and NW 247th

St.