Tentative Work Schedule

December 4, 2019

 

Work in the NW section consists of Grading NW 219th St. (off of NW CR 225) and NW 36th Ave.

 

Work in the SE section consists of Mowing SE 109th & SE 21st Ave.

 

Work in the SW section consists of Shoulder work on SW CR 235, Grading SW 106th St. & SW 104th St. and Mowing SW 163rd

 

 

We received 1 DOC Squad for a total of 5 people and they will be directing traffic for Cleaning out and Digging ditches on SW CR 235