Tentative Work Schedule

March 14, 2024

 

Work in the NE section consists of Busting up Beaver Dams on NE 28th Ave.

 

Work in the NW section consists of Grading NW 82nd Ave., NW 185th St., NW 188th St. and NW 196th St., Mowing the Shoulders of the Road on NW 233rd St. and Prepping NW 38th Ave. to Pave.

 

Work in the SE section consists of Grading SE 38th Ave. and Moving the 50G from the Keystone Landfill to NE 28th Ave.

 

Work in the SW section consists of Grading SW 66th Ave.

 

 

We received 1 DOC (BCSO-JAIL) Officer and he is Assisting in Maintenance

 

We did not receive any Inmates as our other Officer was out Sick