Tentative Work Schedule

March 29, 2022

 

Work in the NE section consists of Grading NE 20th Lane

 

Work in the NW section consists of Grading and packing NW 238th St., NW 178th and NW 205th, Installing a Culvert on NW 71st Ave. and Mowing ROW on NW 27th

 

Work in the SW section consists of Grading SW 180th, SW 132nd, SW 155th and SW 160th, Mowing ROW on SW CR 237 and Mowing SW CR 237, SW CR 18, SW CR 231 and SW 175th

 

We will also be Mowing all County Fire Department sites and County Collection Sites with the Zero Turn Mower

 

 

We received 2 DOC (BCSO-JAIL) Officers and a total of 4 Inmates

 

1 Squad and 2 Inmates will be Picking up Trash and Weed Eating Guardrails on SW CR 231 (Dedan Loop) and SW CR 18

 

1 Squad and 2 Inmates will be Picking up Trash and Weed Eating Guardrails on NW 41st and NW 44th and the Bridge on NW CR 229