Tentative Work Schedule

July 10, 2019

 

Work in the NE section consists of Digging out the outfall ditch on Carter Road and Mowing NE 19th Ave. and NE 28th

 

Work in the NW section consists of Grading NW 44th, NW 41st, NW 35th, NW 209th, NW 110th, NW 105th & NW 193rd, Dig out the ditch on NW 38th Ave., Mow NW 180th, NW 75th & NW 71st and Cut trees out of ditch on NW 61st St off of NW 200th and Haul off debris

 

Work in the SE section consists of Patching pot holes on SE 52nd St. and Mowing SE 144th, E 21st Ave. & SE CR 230A

 

Work in the SW section consists of Grading SW 106th, SW 160th, SW 136th & SW 155th

 

 

We received 2 DOC Squads for a total of 9 people

 

1 Squad will be Picking up trash and Weed eating SE 21st Ave & SE CR 230A

 

1 Squad will be Cleaning & Cutting trees out of ditch on NW 61st Ave