Tentative Work Schedule

December 20, 2022

 

Work in the NW section consists of Grading NW 238th St., NW 25th Ave. and NW 228th St, and Cleaning out Culverts and Crossovers  on NW CR 233

 

Work in the SE section consists of Adding Limerock and Grading SE 125th St. and SE 59th Ave.

 

Work in the SW section consists of Grading SW 105th and Mowing ROW on SW CR 235 and SW 161st St. 

 

 

We received 2 DOC Officers (BCSO-JAIL)and 2 Inmates

 

1 Officer will be going to Lincoln City Park and running off a Squatter and then Picking up trash at all Parks

 

1 Squad will be Picking up Trash and Weed Eating NE 20th Lane in Strawberry Acres