Tentative Work Schedule

June 3, 2019

 

Work in the NW section consists of Grading NW 205th, NW 44th & NW 41st, Patching Pot Holes on NW 223rd St. and Mowing NW CR 229

 

Work in the SE section consists of Grading all dirt roads off SE 21st Ave., Cleaning out the ditch SE CR 325 and Patch a driveway on SE 5th Ave.

 

 

We received 2 DOC Squads for a total of 10 people

 

1 Squad will be directing traffic for Cleaning out a ditch on SE CR 325

 

1 Squad will be Picking up trash and Weed Eating on NW CR 229