Tentative Work Schedule

May 4, 2023

 

Work in the NE section consists of Mowing Sidewalks on NE 15th Ave. & NE CR 125 with the Zero Turn and Mow NE CR 200B

 

Work in the NW section consists of Grading NW 36th Ave., NW 198th St., NW 251st St., NW 228th St. and NW 63rd Ave. and Mowing NW 216th St. and NW CR 200A

 

Work in the SE section consists of Pumping out a Pond on SE 15th Ave. and Loading up Trash Dirt at the Airport and Hauling it away