Tentative Work Schedule

 

August 1, 2018

 

Work in the NW section consists of Limerocking NW 41st Ave., Installing a culvert at 6875 NW 219th Ter. and Limerocking NW 203rd St.

 

Work in the SE section consists of Repairing the ditch, Slowing down the water flow and Patching Driveways on SE 66th St., Grading SE 94th St., Ditch work on SE 11th Ave. and Cutting off SE 38th Ave.

 

Work in the SW section consists of Zipping and adding materials to SW 101set Ave. and Mowing on SW CR 18 going towards Sampson City VFD

 

 

We received 2 DOC Squads for a total of 11 people

 

1 Squad will be repairing a ditch and Patching driveways on SE 66th St.

 

1 Squad will be Patching pot holes on SE 49th Ave. (North of Meng Dairy) and NW 124th St.