Work Schedule

 

Work in the NE section consists of Patching pot holes & driveways

 

Work in the NW section consists of Zipping a road, Pulling Ditches, Patching pot holes & driveways and Installing a culvert

 

Work in the SE section consists of Grading and Mowing

 

Work in the SW section consists of Cutting, Trimming and Chipping trees and limbs

 

 

We received 3 DOC Squads for a total of 14 people

 

1 Squad will be assisting in Cutting, Trimming and Chipping trees and limbs in the SW section

 

1 Squad will be Picking up trash and Weed eating around mailboxes  and guardrails in the SE section

 

1 Squad will be directing traffic for installation of a culvert in the NW section

 

 

1 Squad from The Transition House (3 people) will be assisting in patching pot holes and driveways in the NE & NW section