Tentative Work Schedule

February 19, 2019

 

Work in the NE section consists of Chipping limbs and brush on NE 20th Lane

 

Work in the NW section consists of Grading NW 41st, NW 44th, NW 49th & NW 213th and Digging the ditch on NW CR 235 (Nettle's ditch)

 

Work in the SE section consists of Grading and working on SE 46th Loop

 

Work in the SW section consists of Scooping out Concrete Ditch at the Hampton Lake Boat Ramp (SW 69th St.) and Patching troughs on SW CR 235, SW CR 231 and SW CR 18

 

 

We received  2 DOC Squads for a total of 11 people

 

1 Squad will be assisting in Patching troughs on SW CR 235, SW CR 231 & SW CR 18

 

1 Squad will be assisting in Scooping out the Concrete Ditch at Hampton Lake Boat Ramp on SW 69th St.

 

 

 

-