Tentative Work Schedule

September 11, 2018

 

Work in the NE section consists of Mowing NE 185th

 

Work in the NW section consists of Grading Whitehead Settlement, Installing Crossover pipes on NW 216th , Pulling ditches on NW 41st Ave., Digging ditch on NW 53rd Ave., Patching pot holes on NW 105th, Mowing NW 74th Ave., 215th Way, & 219th St. and Blowing out culverts on NW 203rd St.

 

Work in the SE section consists Grading Crystal Lake Homesites area and SE 49th Ave.

 

 

We received 3 DOC Squads for a total of 17 people

 

1 Squad will be laying Sod at 9118 SW CR 225A

 

1 Squad will be replacing Crossover pipes on NW 216th St.

 

1 Squad will be Patching pot holes on NW 105th