September 23, 2020

 

Work in the NE section consists of Cleaning out the ditches in NE 227th St.

 

Work in the NW section consists of Grading NW 35th, NW 209th, NW 41st., and Mowing NWCR 229A, NW CR 233 and NW 216th St.

 

Work in the SW section consists of Grading SW 168th, SW 137th & SW 144th, Spraying (Fog Seal) on SW 106th Ave. and Mowing SW CR 18 and Chipping limbs on SW CR 231 (Dedan Loop) and on SW CR 18 and Keep limbs off of SW CR 18 when Tree Trimmer cuts the 

 

 

We did not receive any DOC Squads today