Tentative Work Schedule

July 12, 2021

 

Work in the NE section consists of Replacing Crossover pipe on NE 219th St. and Opening up culvert on NE 10th

 

Work in the NW section consists of Grading NW 71st Ave

 

Work in the SE section consists of Grading roads off of SE 8th Ave. and SE CR 21B and Opening up ditches on SE 50th

 

Work in the SW section consists of Grading SW 64th, SW 65th and SW 66th

 

 

We received 2 DOC (BCSO-JAIL) Squads and 5 Inmates and they will be assisting with work at the bridge on Dedan Loop