Tentative Work Schedule

February 17, 2020

 

Work in the NW section consists of Grading NW 177th & NW 62nd Ave.

 

Work in the SE section consists of Cutting up and Cleaning up tree on SE 28th Ave.

 

Work in the SW section consists of Zipping and Fog Sealing on SW 101st Ave., Grading SW 147th and towards Brooker and Cut up and Cleaning up tree near 3 pipes

 

 

We received 3 DOC Squads for a total of 14 people

 

1 Squad will be Picking up trash on SR CR 231 from SR 18 to SW 1161st Ave. and on SW 161st Ave.

 

1 Squad will be assisting with Cutting up and Hauling off a tree on SE 28th Ave. and one near 3 pipes on SW CR 225 

 

1 Squad will be Cleaning the Parks and then Picking up trash on SE 21st Ave.