Tentative Work Schedule

August 26, 2019

 

Work in the NW section consists of Grading NW 251st St. and down NW CR 125, Mow & Clean out ditch on NW 41st Ave., Patch pot holes on NW 198th St. and Mow NW 185th st., NW 84th Ave., NW 188th St., NW CR 225 & NW CR 229

 

Work in the SE section consists of Grading roads off of SE CR 18 and Working on Cutting up & Hauling off a big tree on SE CR 18

 

Work in the SW section consists of Grading and Packing SW 179th, Prepping SW 155th Ave. to limerock and Mowing SW CR 100A and SW 75th Ave.

 

 

We received 3 DOC Squads for a total of 15 people

 

1 Squad will be Picking up trash and Weed eating NW CR 225

 

1 Squad will be Picking up trash and weed eating SW 163rd St.

 

1 Squad will be assisting with Cutting up and Hauling off a big tree on SE CR 18