Tentative Work Schedule

 

July 24, 2018

Work in the NW section consists of Grading & Repairing NW 41st Ave. 

 

Work in the SE section consists of Pull ditches SE 38th Ave., Grade & Add limerock SE 59th St. and Pull ditches in Lincoln City

 

Work in the SW section consists of Grading & adding limerock to SW 92nd St., Add enzymes to SW 101st Ave. and Mow SW CR 231

 

 

We received 3 DOC Squads for a total of 16 people

 

1 Squad will be weed eating on NE 17th Ave., Weed eating and picking up trash on SE CR 230A and SW CR 235 from SR 100 to Brooker.

 

1 Squad will be weed eating the roads off NE CR 225

 

1 Squad will be patching pot holes on SW CR 225A