Tentative Work Schedule

October 27, 2020

 

Work in the NW section consists of Prepping NW 214th St., Mowing ROW on NW 61st St. and Trimming, Cutting limbs, Chipping and Mulching on NW CR 225 and NW CR 125

 

Work in the SE section consists of Grading SE 49th Ave., SE 101st St. & SE 41st Ave., Cleaning out culverts on SE CR 100A, Mowing SE CR 214, SE 109th St. & SE 21st Ave. and Picking up and Hauling off dirt and debris from cleaning out the ditches

 

Work in the SW section consists of Grading SW 132nd Ave.

 

 

We received 2 DOC Squads for a total of 9 people

 

1 Squad will be assisting with Chipping on NW CR 225

 

1 Squad will be Mowing and weed eating SE 3rd Ave. Pond and SE 2nd Ave. Pond in the Keystone Golf & Country Club