Tentative Work Schedule

April 29, 2021

 

Work in the NE section consists of Limerocking NE 247th St. and Traffic Control for putting up Guardrail on NE 28th Ave.

 

Work in the NW section consists of Digging the ditch on NW CR 225, Mowing ROW on NW 178th Loop and Loading trucks at the Market Road pit

 

Work in the SE section consists of Mowing SE CR 21B and SE 8th Ave.

 

Work in the SW section consists of Grading and Watering SW 64th Ave., Grading SW 101st Ave., SW 160th Ave. and SW 136th St. and Opening up a culvert on SW CR 237

 

 

We did not receive any DOC Squads nor Inmates