Tentative Work Schedule

November 30, 2023

 

Work in the NW section consists of Grading NW 71st and NW 41st, Fixing the Apron on NW 188th and Cleaning Up and Moving Culverts at the Market Road Pit

 

Work in the SE section consists of Grading SE 46th Loop, SE 52nd and SE 31st

 

Work in the SW section consists of Grading SW 163rd St., SW 136th St. and SW 137th St., Mowing Shoulders of the Road on SW 46th, SW 41st and SW 38th and Mowing SW CR 237, SW CR 231 and SW CR 18

 

We will also Mow and Weed Eat the Parking Area at the High School (Peaceful Path) 

 

 

We received 2 DOC (BCSO-JAIL) Officers and 2 Inmates

 

1 Officer will be working at the Courthouse

 

1 Officer and 2 Inmates will be working and Cleaning up at the Shop