Tentative Work Schedule

November 17, 2020

 

Work in the NE section consists of Grading NE 173rd St., NE 19th Lane and NE 21st Lane and Patch Pot Holes on NE 219th St. and NE 10th Ave.

 

Work in the NW section consists of Prepping and Spraying NW 124th St., Picking up limbs on NW CR 125 and Mowing NW CCR 125, NW 22nd Ave. and NW 27th Ave.

 

Work in the SE section consists of Grading SE 4th Ave., SE 2nd Ave. and SE 55th St. and Mowing SE 86th St.

 

 

We received 2 DOC Squads for a total of 8 people.

 

1 Squad will be Picking up trash and Weed Eating on NW CR 229

 

1 Squad will be assisting with Patching Pot Holes on NE 219th St. & NE 10th Ave.