Tentative Work Schedule

August 31, 2020

 

Work in the NW section consists of Cutting shoulders on NW CR 225, Patching Pot Holes on NW 219th St. and Mowing NW CR 225 and NW CR 229

 

Work in the SW section consists of Grading SW 163rd and SW 155th, Cutting ROW on SW 139th St., Cleaning out Concrete ditches on SW CR 231 and Mowing SW 75th Ave. and SW CR 100A

 

 

We received 2 DOC Squads for a total of 10 people

 

1 Squad will be assisting with Patching Pot Holes on NW 219th St

 

1 Squad will be Picking up trash and weed eating at intersections of SW CR 18 & SW CR 227, SW CR 18 & SW CR 225A and on SW 180th Pl. & SW CR 114th St

 

County Squad will be handling Traffic Control for work on NW CR 225